Contact Form Demo
Generator and Transformer Protection Cabinets

Renovation Scheme for Generator and Transformer Protection Cabinets, Yongshan No.5 Hydropower Station, Vietnam

Generator and transformer protection cabinet renovation at Yongshan No.5 Hydropower Station in Vietnam replaced a pair of integrated devices with separate ones for each function. The station runs a single 14 MW generator at 11 kV, stepped up to 115 kV, and its 31 secondary cabinets had been in service for more than ten years.

The interesting part is not the hardware count. The original scheme concentrated every generator function on one device, so a single board failure took all of them out at once. The revised scheme gives main protection, backup protection, rotor earth fault protection and measurement and control their own devices, which is what the regional grid operator wanted before it would accept reconnection.

The cabinets stay where they are. The CT assignments are what had to be re-checked.

Generator and transformer protection cabinets at Yongshan No.5 before renovation (illustrative)

Table of Contents

At a Glance: The Generator and Transformer Protection Cabinet Renovation

  • Site: Yongshan No.5 Hydropower Station, Vietnam: one 14 MW generator at 11 kV, stepped up to 115 kV by the main transformer.
  • Inventory: 31 secondary control and protection cabinets, all more than ten years old.
  • Generator side: 87G differential on CT1 and CT2, backup protection on CT3, 64R rotor earth fault, plus a separate measurement and control device.
  • Transformer side: 87T differential on CT4 and CT5, HV backup on CT5, LV backup on CT4, non-electrical quantities (63, 71, 96, 26-O, 26-W) and a station service branch device on CT6.
  • Trip targets: QF1 generator outlet, QF2 transformer HV side, QF3 station service branch.
  • What changed: one integrated device per cabinet becomes a dedicated device per function.
  • Why: a single-point failure on the old layout disabled every generator function at once, and the grid acceptance test looks for exactly that.
  • Next stage: the remaining cabinets show the same age symptoms and were quoted separately.

Device codes follow ANSI/IEEE C37.2-2022. Relay performance and testing reference IEC 60255-1:2022, and generator protection practice is set out in IEEE C37.102-2023. Station-level communication runs on IEC 61850, and the cabinets are built as assemblies to IEC 61439-2:2020.

Project Overview

Yongshan No.5 Hydropower Station is equipped with a generator with a rated capacity of 14 MW and a rated outlet voltage of 11 kV. Electric energy is boosted to 115 kV via the main step-up transformer and then delivered to the power grid.

The secondary equipment of the station has been in operation for more than 10 years and has reached the end of its service life, suffering from serious aging of components, discontinued spare parts, degraded protection performance, and failure to meet current power grid dispatching and hydropower technical specifications. A full upgrade and retrofit of the secondary protection & automation system is required.

This project requires the retrofit of the generator and transformer protection cabinets. Everything else in the inventory stays in place for now, and that boundary shapes every decision described below.

That is the setting for the generator and transformer protection cabinet renovation described below.

Site photos of Yongshan No.5 Hydropower Station

Yongshan No.5 is one of the small hydropower stations where the whole secondary system was supplied as a single package; the hydropower relay protection page covers the protection side of that package in general terms.

Yongshan No.5 hydropower station machine hall (illustrative)
Secondary equipment room at Yongshan No.5 before the retrofit (illustrative)

Original Configuration of Protection & Control Cabinets

The station is originally equipped with a total of 31 sets of secondary control and protection cabinets. The detailed list is shown in the table below:

Serial No.Cabinet No.Cabinet NameDimensionUnitQuantity
11KControl Console800×600 mmSet1
22KCommunication Cabinet800×800 mmSet1
33KG1 Generator Protection Cabinet800×600 mmSet1
44KG2 Generator Protection Cabinet800×600 mmSet1
55KT1 Transformer Protection Cabinet800×600 mmSet1
66KT2 Transformer Protection Cabinet800×600 mmSet1
77KCommon Local Control Unit (LCU) Cabinet800×600 mmSet1
88KNo.1 Circuit Breaker Protection Cabinet800×600 mmSet1
99KNo.2 Circuit Breaker Protection Cabinet800×600 mmSet1
1010KY1 Line Protection Cabinet800×600 mmSet1
1111KY2 Line Protection Cabinet800×800 mmSet1
1212KY3 Line Protection Cabinet800×600 mmSet1
1313KEnergy Metering Cabinet A1800×600 mmSet1
1414KEnergy Metering Cabinet A2800×600 mmSet1
1515KSwitchyard LCU Cabinet A1800×600 mmSet1
1616KSwitchyard LCU Cabinet A2800×600 mmSet1
1717KEmergency Lighting Switch & AC Power Panel800×600 mmSet1
1818KFire Alarm Control Cabinet800×600 mmSet1
1919KOptical Fiber Communication Cabinet800×600 mmSet1
2020KDispatching Switch Cabinet800×600 mmSet1
2121KSpare Cabinet800×600 mmSet1
2222KDC Feeder Panel (400 Ah)800×600 mmSet1
2323KDC Charging Panel (400 Ah)800×600 mmSet1
24~2624K~26KBattery Cabinet (400 Ah)800×600 mmSet3
27~2827K~28KCommunication DC Panel (200 Ah)800×600 mmSet2
29~3129K~31KSpare Cabinet800×600 mmSet3

Original Protection Function List (ANSI Standard)

The original protection system covers full fault diagnosis functions for generators, main transformers and outgoing lines, as listed in the table below:

CodeEnglish Name
FRFault Recorder
I/OMeasuring and control transducer unit
EMEnergy meter
PMACAC sample device
21/21NDistance protection relay or phases short circuit and three levels earthing
24Over exciting protection
25Synchronizing check device
26-OTransformer oil thermal overload protection
26-WTransformer winding thermal overload protection
27/59Undervoltage/overvoltage protection
32Directional reverse power relay
40Loss of excitation protection
46Generator negative-sequence current protection
26/49Overload relay
50BFInoperated protector for circuit breaker
50/51Instantaneous/time overcurrent protection
51NTime earthing overcurrent protection
59Overvoltage protection
59NEarthing protection
63Gas protection
64RRotor earthing-fault protection
64S+27TN100% stator earthing-fault protection
67/67NDirectional overcurrent and earth-fault protection
71Low oil level protection
74Trip circuit supervision relay
78Out-of-step protection
79/25Autoreclosing and synchronism checking relay
87GGenerator differential protection
87GTTransformer-generator differential protection
87TTransformer differential protection
96Oil pressure relay

Original Scheme vs. Optimized Revised Scheme

Both schemes cover the same functions. A generator and transformer protection cabinet renovation usually turns on how those functions are distributed, not on which ones are present.

Both schemes cover the same functions. A generator and transformer protection cabinet renovation usually turns on how those functions are distributed, not on which ones are present.

Original On-site Scheme for Generator and Transformer Protection Cabinets

ItemEquipment NameModelUnitQty
ⅠGenerator Protection & Control Cabinet–Panel1
1Generator-Transformer Unit Protection DeviceDEP-531NSet1
2Generator Main Protection DeviceDEP-561NSet1
3Generator Backup Protection DeviceDEP-565NSet1
4Cabinet Body & Accessories2260800600Set1
ⅡTransformer Protection & Control Cabinet–Panel1
1Transformer Main Differential Protection DeviceDEP-531NSet1
2Transformer Backup Protection DeviceDEP-535NSet1
3Transformer Non-Electrical Quantity Protection DeviceDEP-539BSet1
4Station Service Transformer Protection DeviceDEP-536NSet1
5Cabinet Body & Accessories2260800600Set1

After technical discussion and review, the scheme is adjusted to separate main protection, backup protection, rotor earth fault protection and measurement & control functions into independent cabinets, improving system redundancy, operation reliability and maintenance accessibility.

ItemEquipment NameUnitQty
ⅠGenerator Protection & Control CabinetPanel2
1Generator Differential Protection DeviceSet1
2Generator Backup Protection DeviceSet1
3Generator Rotor Earth Fault Protection DeviceSet1
4Generator Measurement & Control DeviceSet1
5Cabinet Body & Full AccessoriesSet1
ⅡTransformer Protection & Control CabinetPanel2
1Transformer Main Differential Protection DeviceSet1
2Transformer HV Side Backup Protection DeviceSet1
Transformer LV Side Backup Protection DeviceSet1
3Transformer Non-Electrical Quantity Protection DeviceSet1
4Station Service Transformer Branch Protection DeviceSet1
5Cabinet Body & Full AccessoriesSet1

Reasons for Scheme Optimization

Three arguments drove the change, and only one of them is about hardware age. A hydropower protection retrofit has to answer the grid operator, the maintenance crew and the outage planner at the same time.

Compliance with Current Technical Codes for Small & Medium Hydraulic Generators

For small-capacity generators such as the 14 MW unit of this station, complete and independent protection configuration is mandatory per industry technical specifications.

The original integrated single-cabinet design concentrates all protection functions on a small number of devices; single-point component failure will disable all generator protections. The revised split cabinet layout realizes physical isolation of main protection, backup protection and rotor earth fault protection, eliminating single-point failure risks and meeting power grid grid-connection acceptance requirements.

Function, CT Sampling & Trip Logic of Each Protection Device

Start with the CTs.

Before going device by device, the CT allocation the whole scheme depends on:

  • CT1: generator terminal, paired with CT2 for 87G.
  • CT2: generator neutral side.
  • CT3: generator terminal; feeds the backup device, and substitutes for CT4 in the alternative 3-winding differential.
  • CT4: transformer LV side, for 87T and LV backup.
  • CT5: transformer HV side, for 87T and HV backup.
  • CT6: station service branch.
Generator and transformer protection scheme with CT locations and trip targets (illustrative)

Generator Protection System

Generator Differential Protection Device (ANSI 87G)

Sampling CT1 (Generator Terminal) and CT2 (Generator Neutral) to detect internal winding short-circuit and inter-turn faults of the generator.

It trips generator outlet circuit breaker QF1 upon fault detection.

Generator Backup Protection Device

The generator backup device integrates the following protection logics:

ANSI CodeProtection Function Description
67/27/59directional overcurrent blocked by composite voltage
49overload protection
46negative-sequence overcurrent protection
81U+27under-frequency protection
81O+27over-frequency protection
64S100% stator earth fault protection
59overvoltage protection
27undervoltage protection
32reverse power protection
40loss of excitation protection

Sampling CT3 at generator terminal; trips QF1 for external short-circuit and abnormal operating conditions.

Generator Rotor Earth Fault Protection Device (ANSI 64R)

Monitors insulation status of rotor winding: issues alarm signal for single-point rotor earth fault; trips QF1 for double-point rotor earth fault to avoid rotor shaft magnetization and severe unit vibration damage.

Generator Measurement & Control Device

Collects real-time operating data including generator outlet 3-phase voltage, 3-phase current, active/reactive power, power factor and frequency.

It receives remote opening/closing commands for QF1 from central control room and uploads status signals to station LCU system.

Transformer Protection Methods

Transformer Main Differential Protection Device (ANSI 87T)

Standard sampling scheme: CT5 (HV side) and CT4 (LV side), detects internal winding and lead faults of the transformer, and trips QF1 (LV side), QF2 (HV side) and QF3 (station service branch) simultaneously.

Alternative 3-winding differential scheme: If no space is available to install two independent groups of CTs at CT4 position (one for differential protection, one for LV backup protection), 3-winding differential logic can be adopted to sample CT3 (generator side), CT5 (HV side) and CT6 (station service branch), with identical trip logic.

Transformer HV Side Backup Protection Device

The transformer HV side backup device integrates the following logics:

ANSI CodeProtection Function Description
67/51/27/59composite voltage blocked directional overcurrent
51inverse-time overcurrent
49winding & oil overload protection
67N/51N/59Nneutral directional & neutral voltage blocked earth fault protection
59overvoltage
27undervoltage
59Nneutral overvoltage
60PT circuit breakage supervision
74trip circuit supervision

Sampling CT5 at HV side; only trips HV side circuit breaker QF2 when fault occurs.

Transformer LV Side Backup Protection Device

The LV side backup device uses the same protection logics as the HV side:

ANSI CodeProtection Function Description
67/51/27/59composite voltage blocked directional overcurrent
51inverse-time overcurrent
49overload
67N/51N/59Nneutral earth fault protection
59/27voltage protection
60PT breakage monitoring
74trip circuit supervision

Sampling CT4 at LV side; trips QF1 (main LV outlet) and QF3 (station service branch) for LV side faults.

Transformer Non-Electrical Quantity Protection Device (ANSI 63 Gas, 71 Low Oil Level, 96 Pressure Relief, 26-O/26-W Thermal Protection)

The non-electrical quantity device accesses all transformer body non-electrical signals:

ItemFunction Status
light gasalarm
heavy gastrip
high oil temperaturetrip/alarm
winding overtemperaturetrip/alarm
low oil levelalarm
pressure relief valve actiontrip

Severe faults trigger tripping of QF1, QF2 and QF3 on all three sides.

Station Service Branch Protection Device

The station service branch device integrates the following logics:

ANSI CodeProtection Function Description
50/51/27/59instantaneous & time-delayed composite voltage blocked overcurrent
51inverse-time overcurrent
49overload protection
51N/59Nneutral earth fault protection
60PT breakage supervision
74trip circuit supervision

Sampling CT6 of station service branch; only trips QF3 to isolate branch faults without affecting main transformer and generator.

Improved Operation & Maintenance Efficiency

Separated layout of main protection, backup protection, rotor earth fault protection and measurement & control devices allows independent inspection, calibration and replacement without mutual interference.

Only the faulty device needs to be decommissioned during maintenance, while other protections remain in service, greatly shortening unit outage duration and reducing power generation loss.

Compliance with Grid Grid-Connection Standards

Regional power grid dispatching authorities enforce strict redundancy requirements for small hydropower grid-connected equipment.

The original integrated single-cabinet scheme fails grid connection acceptance due to insufficient fault isolation capacity.

The revised split independent cabinet design features clear fault tripping logic and adequate protection redundancy, which can pass grid special acceptance at one time.

Supplementary Retrofit Recommendation for the Rest of the Station

The two cabinets described above were the urgent part of a wider Vietnam hydropower retrofit. What follows is the case for turning this into a protection cabinet upgrade case that covers the rest of the station while it is already open.

The station has been in operation for more than 10 years. All secondary cabinets listed in the inventory, including line protection cabinets, switchyard LCU cabinets, common LCU cabinets, communication power panels, metering cabinets, dispatching switch cabinets and DC system panels, suffer widespread component aging.

Electronic capacitors, relays and main control boards face high risk of failure, and original spare parts have been discontinued by manufacturers. Long-term operation with degraded equipment may lead to protection failure, monitoring loss and communication interruption, posing major safety hazards to the power station.

It is recommended to complete full replacement of all aged secondary cabinets within this retrofit project, realizing full-station secondary system upgrade with unified hardware platform, communication protocol and human-machine interface, to achieve intelligent transformation of the station. After retrofit, the system will deliver the following benefits:

  1. Integrated networking of full-station protection, measurement & control, fault recording and metering equipment, fully meeting remote dispatching and four-remote signal upload requirements;
  2. Unified hardware platform reduces spare part categories and long-term operation & maintenance costs;
  3. Complete fault recorder and Sequence of Event (SOE) functions support rapid fault tracing and analysis;
  4. All equipment complies with IEC 61850 digital communication standard, compatible with long-term unattended and minimally-attended operation mode of hydropower stations.

That list is the argument for doing the whole station at once rather than in stages. The generator and transformer protection cabinet renovation described above was the first slice.

Two cabinets now, the rest later.

Frequently Asked Questions

Why split one integrated device into several?

This generator and transformer protection cabinet renovation splits the functions because on the original layout every generator function lived on one device, so a single board failure removed all of them together. Splitting main protection, backup protection, rotor earth fault protection and measurement and control into separate devices means a fault in one leaves the others running, and a technician can pull one device for calibration without taking the unit out of service.

When does the 3-winding differential scheme apply?

When there is no room at the CT4 position for two independent CT groups. The standard scheme samples CT5 and CT4; if CT4 cannot carry both the differential and the LV backup function, the relay samples CT3, CT5 and CT6 instead and applies 3-winding differential logic. Trip targets stay identical.

Does the renovation change the trip matrix?

The targets stay the same: QF1 for the generator outlet, QF2 for the transformer HV side and QF3 for the station service branch. What changes is which device issues the trip: rotor earth fault goes to its own relay instead of sharing a board, and the branch device trips QF3 only, so a branch fault no longer puts the main transformer and generator at risk.

What happens to the other cabinets?

They were surveyed and quoted, not replaced in this stage. Line protection, switchyard and common LCU, metering, dispatching switch and DC panels all show the same age symptoms (electrolytic capacitors, auxiliary relays and main control boards), and the recommendation on file is to replace them while the station is already shut down.

What drives the outage plan in a job like this?

In a generator and transformer protection cabinet renovation the schedule is set by CT availability, not cabinet delivery. Every device in the revised scheme depends on a specific CT, and the two cases where CT4 cannot be shared are what push the schedule. Confirming the CT allocation against the existing switchgear before the cabinets arrive is the step that decides whether the outage holds.

Technical References

StandardEditionWhat it governs hereWhere it applies
ANSI/IEEE C37.22022Device function numbers (87G, 87T, 64R, 63, 71, 96, 26-O, 26-W)Function list and cabinet labelling
IEC 60255-12022General requirements for measuring relays and protection equipmentDevice performance and acceptance
IEC 60255-187-12021Functional requirements for differential protection87G and 87T setting and testing
IEEE C37.1022023Guide for AC generator protectionGenerator function selection
IEC 61850SeriesCommunication networks and systems for power utility automationStation-level data exchange
IEC 61439-22020Low-voltage switchgear and controlgear assembliesCabinet construction
IEC 605291989+AMD1:1999+AMD2:2013Degrees of protection provided by enclosuresCabinet IP rating

Editions are the ones current at the time of writing. Check the version named in the project specification before you order against this page.

Send the single-line diagram, the CT list and the existing cabinet inventory, and the generator and transformer protection cabinet renovation can be quoted against the scheme you already have.

About Author
Leno Zhang
Hello, I'm Leno Zhang. I have 15 years of experience in the power relay protection industry with extensive pre-sales and after-sales project experience. Our company specializes in various complete sets of relay protection and automation equipment. I can assist customers in solving all practical on-site project challenges and provide optimal integrated solutions.
Tell Us Your Requirement
Contact Form Demo

High Quality

Stable performance, reliable design, ensuring safe operation for power system protection and grid stability.

Fast Delivery

Timely delivery to support your urgent orders and project schedules efficiently and professionally at any time.

Best Warranty

Professional Warranty: Reliable after-sales support for stable relay protection and long-term customer satisfaction.