-
Leon Zhang Sales Manager
-
Email: sale@relayprotect.com
-
Phone/WhatsApp: +86 13655813266

Secondary Equipment in PV Power Generation: CT to SCADA
What is secondary equipment in a PV power plant?
Secondary equipment in a PV power plant is everything that measures, decides, records and reports, while primary equipment carries the current. The array, inverter, step-up transformer and MV collection feeders do the electrical work; the secondary system tells the plant what those assets are doing and trips a breaker when one fails. The dividing line is the CT and VT secondary terminals: upstream is primary, downstream is the wiring into a relay, the relay itself, the trip circuit and the network carrying events to an operator. Owners learn this distinction late – a plant can have sound primary equipment yet fail commissioning because one CT polarity was reversed, protection settings were never loaded, or the SCADA point list does not match the installed panels. Those are all secondary problems, easy to overlook in procurement and expensive to add later. The plant network follows IEC 61850. Setting review and quotation within 12 hours, MOQ 1, 7-15 working days.
Secondary equipment in a PV power plant is everything that measures, decides, records and reports, while the primary equipment carries the current. The array, the inverter, the step-up transformer and the MV collection feeders do the electrical work. The secondary system tells the plant what those assets are doing, and it is what trips a breaker when one of them fails.
Owners usually learn this distinction late. A plant can be built with sound primary equipment and still fail its commissioning tests because the CT polarity was reversed on one bay, the protection settings were never loaded, or the SCADA point list does not match the panels that were actually installed. All three are secondary-side problems.
Where Primary Ends and Secondary Begins
The dividing line is the CT and VT secondary terminals. Everything upstream of those terminals is primary: busbars, cables, breakers, transformers, instrument transformers. Everything downstream is secondary: the wiring that carries a scaled-down current into a relay, the relay itself, the trip circuit that opens the breaker, and the network that carries the resulting event to an operator.
This boundary matters commercially. Primary equipment is specified by ratings and tested at the factory. Secondary equipment is specified by function and proven on site, after the primary equipment is already energised or about to be. A missing secondary function is easy to overlook in a procurement review and expensive to add later.

The Signal Chain Inside a PV Plant
Four stages carry one fault from the array to the control room. Each stage has its own device and its own failure mode.
- Measurement. Core balance CTs on the MV feeders, phase CTs on the transformer bushings, VTs on the busbar. A reversed or open CT secondary makes every downstream decision wrong, which is why polarity is checked before the relay is commissioned, not after.
- Decision. The protection relay compares measured values against settings and decides whether to trip. In a PV plant this is usually a multifunction numerical relay serving the feeder or the step-up transformer, plus a separate unit for grid-code functions at the point of interconnection.
- Action. The trip circuit energises the breaker shunt trip coil. It is a small circuit with an outsized role: a blown trip fuse or a loose terminal leaves a relay that measures correctly and does nothing.
- Record and report. The relay writes an event, the fault recorder captures the waveform, and the gateway forwards both to SCADA and to the dispatch centre.
Most “the relay failed” reports turn out to be stage one or stage three. The relay measured the wrong current, or it decided correctly and the trip path was open.
Selecting a relay for a live project?
Send the system voltage, CT ratio and tripping scheme. Our engineers confirm the model and reply within 12 hours.
Panels That Make Up the Secondary System
A utility-scale PV plant typically organises the secondary system into a small set of panels. The exact count follows the plant layout, but the functions do not change much between projects.
- Main transformer protection panel. Differential protection, backup overcurrent and earth fault, voltage and frequency functions, breaker failure. Related: 87T transformer differential relay.
- Busbar protection panel. Bus differential where the yard has a dedicated MV or HV busbar with more than one source. See 87B bus differential protection.
- Feeder protection panels. One per MV collection feeder, carrying overcurrent, earth fault and, where the grid code requires it, directional and distance elements. Background on scheme selection sits on the 33 kV protection relay page.
- Grid interface panel. The functions the utility witnesses: over and under voltage, over and under frequency, rate of change of frequency, reverse power and anti-islanding.
- Measurement and control units. One per inverter transformer or box-type substation, handling local measurement, breaker control and signal collection. See the pad-mounted transformer monitoring unit.
- Fault recording panel. Captures voltage and current waveforms and digital status for post-event analysis. A digital fault recorder stores the few cycles around a trigger that a relay event log cannot.
- Communication and time synchronisation panel. Switches, gateways and the clock source that keeps every device on the same timestamp.
- DC supply and UPS. The battery system that keeps all of the above alive when the plant is de-energised, which is exactly when they are needed.
Measurement and Control at the Box Substation
The inverter transformer, or box-type substation, is where the plant has the most devices and the least supervision. Each unit has its own protection and its own measurement, and a 100 MW plant can have dozens of them.
A measurement and control unit at this level collects three-phase current and voltage, transformer temperature, and the status of the LV and MV breakers. It reports upward over the plant network and accepts commands downward. When it is missing or misconfigured, the plant loses visibility of a whole block of generation without losing the generation itself, so the failure stays hidden until someone compares actual output against the SCADA total.

The Inverter Interface Is Secondary Equipment
The inverter carries and converts power, so it belongs to the primary side. What it reports does not. Every value an inverter exposes is a secondary signal, and the plant is only as observable as that interface is complete.
A workable design uses two channels, and keeps them separate. Hard-wired contacts carry what must work when software does not: emergency stop, fire trip, key interlock, and the status of the MV breaker that the inverter depends on. The data channel carries what an operator needs to run the plant: DC and AC measurements, internal temperature, fault codes, availability state, and the active and reactive power setpoint coming down from the plant controller.
Keeping both is not redundancy for its own sake. A data link fails silently. If a network command is the only way to stop a block of inverters, then one failed switch removes that ability, and nobody notices until the moment it is needed.
The register map is a deliverable, not paperwork. Each inverter supplier publishes a map of its own registers, and the plant controller carries its own tag list. Signals disappear in the mapping between the two. Ask for the as-built point list at handover and check it against the controller configuration, because a missing tag looks exactly like a healthy device that never reports anything.
Polling also sets the resolution of history. SCADA reads on a cycle, so a fault that appears and clears between two polls exists only in the inverter’s own log. That is why inverter logs, relay events and recorder waveforms have to be reconciled by timestamp rather than read separately.
Where a box substation needs its own gateway rather than a direct link to the plant controller, a distribution terminal unit handles collection and forwarding: see the IEC 61850 distribution terminal unit. The protocol families behind these links, and where each one belongs, are compared in Modbus and IEC 61850 substation communication protocols.
Protocols and Network Architecture
Three protocol families appear in a PV plant, and they do different jobs. Knowing which one carries what shortens every troubleshooting call.
- Station bus. IEC 61850 for protection and control devices, carrying reporting and control between relays and the station computer. Products built for this environment are listed under IEC 61850 transformer protection relay.
- Process bus. Sampled values where the design replaces copper CT wiring with a digital stream. It changes the commissioning sequence, because the merging unit becomes part of the measurement chain.
- Telecontrol. IEC 60870-5-104 or DNP3 from the plant gateway to the dispatch centre. This link carries a reduced point list, so a signal can exist in the plant SCADA and still be absent at the utility.
Network redundancy is a design decision, not an accessory. A single ring with no alternative path turns one failed switch into a plant-wide loss of visibility, at the same moment the operators need it most.
Time Synchronisation
Every event in a plant is timestamped, and the value of those timestamps depends entirely on a common clock. When devices drift apart, the sequence of a trip becomes unreadable: a feeder relay appears to operate before the transformer relay that actually saw the fault first.
Two practical rules apply. Give the plant one time source and distribute it, rather than letting each device free-run. And check the clock during commissioning, not after the first disturbance, because a site with drifting clocks produces post-event reports nobody can defend.
DC Supply and Auxiliary Power
The secondary system runs on station DC, backed by a battery. This is the one subsystem whose failure is invisible while the plant is operating and total when it is not. A healthy plant with a flat battery cannot trip a breaker during a grid disturbance.
Two checks catch most of the risk: a battery capacity test at the specified discharge rate, and a trip-circuit supervision function left enabled in the relay so an open trip coil is reported before a fault occurs. Both are secondary-side items and both are frequently deferred.
What Storage Changes on the Secondary Side
Adding a battery system changes the secondary design more than it changes the primary one. The plant stops being a single source feeding one direction, and several assumptions written into the protection settings no longer hold.
- Fault current can arrive from the storage side. A power conversion system can feed a fault as well as the grid can. Elements that assume one direction of flow, or one magnitude of fault current, need directional or dual-setting treatment.
- Loss of mains detection has two owners. Both the PV inverters and the storage converter must detect an island, and neither setting can mask the other. This is tested with storage online and offline, because the plant behaves differently in each case.
- New signals enter the point list. State of charge, cell temperatures, converter mode and battery management alarms are not protection quantities, but they are operational ones, and the utility often wants a subset of them at the dispatch interface.
- Interlocks have to be hard-wired. A converter must not energise into an open or earthed circuit. That interlock belongs in the enable circuit, wired from breaker and isolator status, not left to a software condition that a communication failure can clear.
- Fire and gas detection gets a trip path. Storage enclosures carry their own detection. The path from that detection to the converter and to the MV breaker is a secondary circuit, and it is proven by test, not by configuration review.
- Battery DC is not station DC. The two systems look similar on a drawing and must stay separate. Sharing a battery between the power conversion system and the protection supply puts the protection supply at the mercy of a cycling load.
Commissioning grows accordingly. The trip matrix is tested for every source combination, battery management points are proven end to end, curtailment response is checked against state of charge, and the whole sequence is repeated with the storage system isolated. A plant that only tests with storage online has not tested the configuration it will run in during a maintenance outage.
For how the PV side of the plant is laid out before storage is added, see photovoltaic solar power systems.
Fault Recording and Event Logs
Relay event logs and fault recorder waveforms answer different questions. The event log tells you which element operated and when. The waveform tells you what the current and voltage actually looked like, which is the only way to separate a real fault from a maloperation caused by inrush, CT saturation or a harmonic source such as the inverter front end.
Keep both, and make sure they share a time base. A plant that can produce the waveform but cannot line it up with the relay event will spend days on a fault that should take an hour.
Commissioning Checks That Belong to the Secondary System
These are the checks that decide whether the plant will respond correctly on its first fault. They are all secondary-side, and they are all done after the primary equipment is in place.
- CT ratio and polarity verification at the relay terminals, per bay, recorded against the drawing.
- Secondary injection into every protection element with the as-built settings loaded, not the design settings.
- Trip test from relay output to breaker, proving the trip coil actually opens the breaker.
- Point-to-point signal test between panel and SCADA, matching the approved point list.
- Time synchronisation check across devices, plus verification that the clock survives a power cycle.
- Battery discharge test and trip-circuit supervision verification.
- Communication redundancy test, removing one link and confirming the plant stays visible.
Common Failures on the Secondary Side
In practice the same handful of faults recur across PV projects. None of them is exotic, and all of them are found by the checks above.
- Reversed CT polarity on one bay, which makes directional elements see the fault on the wrong side.
- Loose CT terminal in a box substation, producing an intermittent open circuit that looks like a relay fault.
- Design settings left in the relay instead of as-built settings after a late coordination change.
- Water ingress and condensation in outdoor cabinets, degrading terminals and wiring over a few seasons.
- Earthing and shielding problems that let inverter switching noise into measurement circuits.
- Point lists that were never updated after a design change, so the operator cannot see a device that exists.

What to Specify in an RFQ
A secondary equipment RFQ is more useful when it separates functions from hardware. Describe what each panel must do, then let the supplier propose the device. Three items are worth stating explicitly: the grid-code functions the utility will witness, the protocol and point list for the upper link, and whether the design uses a process bus.
Also state the documentation package. Wiring diagrams, terminal lists, as-built settings files and test records are part of the delivery, not a favour after commissioning. A plant that receives hardware without them pays for the gap during the first outage.
For the protection scheme that sits on top of this equipment, see solar substation protection schemes. For plant-level architecture and equipment lists, the PV power system solution page covers the primary side, and the substation protection relay range lists the devices that populate these panels.
Frequently Asked Questions
What counts as secondary equipment in a PV plant?
Protection relays, measurement and control units, fault recorders, communication and time synchronisation equipment, the station DC and UPS system, and the wiring that connects them to CTs, VTs, breakers and the control room. Anything that measures, decides, records or reports rather than carrying load current.
Is the inverter part of the secondary system?
No. The inverter is primary equipment, because it carries and converts the power. Its control interface, the signals it exchanges with the plant controller, and the measurement unit that reports its output all belong to the secondary side.
Why does CT polarity matter so much?
Directional and differential elements compare currents by direction. A reversed secondary connection makes the relay measure the fault as a load condition, so it either fails to operate or operates on the wrong zone. Polarity is a wiring fact, checked at commissioning and recorded bay by bay.
Do all PV plants need a fault recorder?
Not all, but the ones without it lose the ability to explain a maloperation. Relay event logs give timestamps and element names. Waveforms give the actual current and voltage, which is what separates a genuine fault from inrush, saturation or harmonic interference.
How is secondary equipment tested before energisation?
By secondary injection with as-built settings, trip tests to the breaker, point-to-point signal tests against the approved point list, time synchronisation checks, a battery discharge test and a communication redundancy test. All of these are done with the plant de-energised, and all of them are recorded.
Questions on the settings in this guide go to the engineering team, normally answered the same working day.




