-
Leon Zhang Sales Manager
-
Email: sale@relayprotect.com
-
Phone/WhatsApp: +86 13655813266
Project Record: 93 Installations in 43 Countries
This page documents 93 protection relay and panel installations delivered in 43 countries, from 6 kV industrial feeders to 220 kV utility substations. The April 2025 3 MW rooftop PV plant in Hebei is used first as a worked example: it shows what a full secondary-equipment scope looks like from enquiry through to joint commissioning with two dispatch centres. The country-by-country project record follows below.
In April 2025 we supplied and commissioned all of the secondary equipment for a 3 MW rooftop photovoltaic plant at the Hebei Tiefeng Environmental Protection Science and Technology Park. The plant was energised and connected to the grid on 28 April 2025, after joint communication commissioning with both the prefecture-level and the county-level dispatch centres.
Project at a Glance
| Client | Hebei Tiefeng Environmental Protection Science and Technology Park, Hebei Province, China |
|---|---|
| Plant | Rooftop photovoltaic, 3 MW |
| Scope | All secondary equipment for the PV plant: protection, monitoring and communication |
| Our work | Complete layout and engineering of the distributed PV monitoring system, supply of the devices, and on-site communication commissioning |
| Grid interface | Joint commissioning with prefecture-level dispatch and county-level dispatch |
| Connected | 28 April 2025 |
| Schedule driver | The owner needed the plant connected before the 30 April policy cut-off for the tariff in force at the time |
| Outcome | Commissioning completed and the plant connected within the required window |
What “All Secondary Equipment” Covers
On a grid-connected PV plant the primary equipment – modules, inverters, transformers, switchgear – is only half of the installation. Everything that measures, protects, signals and reports is secondary equipment, and the plant cannot be energised until that layer has been proven against the grid operator’s requirements. On this project the scope covered three functions:
- Protection at the point of connection and on the collector circuits, including the interfaces the grid operator requires at the point of common coupling.
- Monitoring of the distributed PV plant as a whole – inverter status, string and combiner data, metering, alarms – presented in one system rather than a set of independent boxes.
- Communication to the dispatch centres, which is where most PV projects lose time.
Why Dual-Dispatch Commissioning Is the Real Schedule Risk
In China a distributed plant of this size reports to two dispatch centres at once: the prefecture-level centre and the county-level centre. Each has its own point list, its own signal naming and its own acceptance procedure. A plant can be physically complete and still be unable to connect because one of the two centres has not accepted the telemetry and telecontrol signals.
That is why the April deadline was a commissioning problem before it was an equipment problem. The work that has to be finished before the connection date is the point-by-point verification of every analogue value, every status signal and every control command against both dispatch point lists, followed by the communication test itself. When those items are left to the week of the deadline, the deadline is missed.
How the Dates Were Met
The sequence that made 28 April achievable was:
- The monitoring and communication architecture was fixed first, so the device list and the point lists could be agreed with both dispatch centres before hardware arrived on site.
- Devices were supplied against that fixed architecture rather than being re-specified during installation.
- Communication commissioning with the two dispatch centres was treated as its own work package with its own test record, not as the last item on the electrical commissioning list.
This is the same sequence we apply to export projects, where the equivalent risk is a utility or an EPC contractor whose interface specification arrives late.
What This Means for a Buyer Outside China
The technical content of the job is not unusual: protection at the point of connection, monitoring across a distributed plant, and a communication link to a control centre. What the project demonstrates is the part that is hard to buy from a catalogue – getting an interface specification agreed, and getting a third party to accept signals against it on a fixed date.
If your project has a utility interface, a dispatch or SCADA point list, or a fixed connection date, send the single-line diagram and the point list with your enquiry. The protection functions and the device configuration can be settled against the documents before any hardware is ordered.
Project Track Record
This is the delivered record behind the catalogue: 93 completed projects in 43 countries outside China. Not enquiries, not framework agreements – substations and plants where our relays and panels are in service. The voltages run from 6 kV industrial distribution up to 220 kV substations, across mining, steel, cement, oil and gas, ports, utilities, renewables and commercial buildings.
Projects are listed by country. Client names are available on request under a reference agreement, because most of these installations are owned by utilities and industrial groups that do not publish their suppliers.
Jump to a country: Myanmar, Vietnam, Indonesia, Laos, Thailand, Cambodia, Philippines, Malaysia, Pakistan, Bangladesh, Nepal, Bhutan, India, Tajikistan, Kazakhstan, Kyrgyzstan, Azerbaijan, Armenia, Turkmenistan, Lebanon, Oman, Saudi Arabia, Qatar, United Arab Emirates, Iraq, Bahrain, DR Congo, Nigeria, South Africa, Angola, Egypt, Ethiopia, Ghana, Tanzania, Zambia, Russia, Germany, Turkey, Bolivia, Brazil, Mexico, Mongolia, South Korea.
Southeast Asia: 33 projects in 8 countries
| Country | Projects | Voltage | Representative application |
|---|---|---|---|
| Myanmar | 10 | 35-110 kV | Mine and industrial substations, cement plant, 4 x 7500 kW hydro station |
| Vietnam | 8 | 6-110 kV | Steel plants, hydro stations, 2 x 600 MW thermal plant, mine substations |
| Indonesia | 4 | 20-150 kV | Jakarta power plant; thermal plant automation; hydro stations |
| Laos | 3 | 22-35 kV | Water treatment plant expansion and pumping station, Vientiane; coal mine substation |
| Thailand | 3 | 22-115 kV | Bangkok commercial district; industrial estate drainage pumping; steel mill substation |
| Cambodia | 2 | 22-35 kV | Coastal resort; provincial grain storage |
| Philippines | 2 | 13.8-34.5 kV | Wholesale market and hotel, Metro Manila |
| Malaysia | 1 | 11 kV | Hotel tower, Kuala Lumpur |
South Asia: 7 projects in 5 countries
| Country | Projects | Voltage | Representative application |
|---|---|---|---|
| Pakistan | 3 | 11-220 kV | Hotel and airport distribution, Islamabad; generation plant auxiliary systems |
| Bangladesh | 1 | 11 kV | 5 x 2000 kW captive generation, Jamuna Group |
| Nepal | 1 | 12 kV | Distribution room, Patan |
| Bhutan | 1 | 11 kV | Golf course development, Thimphu |
| India | 1 | 11 kV | Deva hydro power plant |
Central Asia and the Caucasus: 10 projects in 6 countries
| Country | Projects | Voltage | Representative application |
|---|---|---|---|
| Tajikistan | 3 | 10-110 kV | Pakrut and Hamadoni substations; underground mine distribution |
| Kazakhstan | 2 | 6-35 kV | River pumping station; non-ferrous metal smelter, Almaty region |
| Kyrgyzstan | 1 | 35 kV | Gold mine processing plant substation |
| Azerbaijan | 2 | 35 kV | National university, Baku; Caspian oil and gas facility |
| Armenia | 1 | 10 kV | Department store, Yerevan |
| Turkmenistan | 1 | 35 kV | Oil and gas processing plant |
Middle East and the Gulf: 12 projects in 7 countries
| Country | Projects | Voltage | Representative application |
|---|---|---|---|
| Lebanon | 3 | 11-15 kV | Port power distribution and cargo terminal, Beirut and Tripoli |
| Oman | 3 | 11-33 kV | Port distribution centre and urban refurbishment, Muscat; hotel |
| Saudi Arabia | 2 | 33-110 kV | Substations, Sakaka and Al-Jalamid |
| Qatar | 1 | 66 kV | Substation |
| United Arab Emirates | 1 | 11 kV | Higher education campus, Abu Dhabi |
| Iraq | 1 | 33 kV | Substation automation system |
| Bahrain | 1 | 11 kV | Date palm plantation distribution, Manama |
Africa: 17 projects in 9 countries
| Country | Projects | Voltage | Representative application |
|---|---|---|---|
| DR Congo | 6 | 11-33 kV | Substations, hydro station, sulphuric acid plant, 6 MW waste heat power, copper-cobalt mine |
| Nigeria | 3 | 33 kV | Plateau State substation; Abuja cold storage; paper mill |
| South Africa | 2 | 11-33 kV | Football stadium power supply, Johannesburg and Mbombela |
| Angola | 1 | 60 kV | 11,000 V grid connection station, Luwango |
| Egypt | 1 | 11 kV | Production line power distribution |
| Ethiopia | 1 | 15 kV | Electrical testing facility, Addis Ababa |
| Ghana | 1 | 33 kV | Cement plant substation |
| Tanzania | 1 | 35 kV | Steel plant substation |
| Zambia | 1 | 33 kV | 2 x 150 MW power plant, Soke |
Europe: 5 projects in 3 countries
| Country | Projects | Voltage | Representative application |
|---|---|---|---|
| Russia | 2 | 35-110 kV | Substations, Ussuriysk and Novopu |
| Germany | 1 | 10 kV | 2 x 7 MW coal generating unit |
| Turkey | 2 | 33 kV | District heating; waste-to-energy plant retrofit, Antalya |
The Americas: 3 projects in 3 countries
| Country | Projects | Voltage | Representative application |
|---|---|---|---|
| Bolivia | 1 | 6 kV | Cement grinding station, EP project |
| Brazil | 1 | 13.8 kV | Food factory, Kraft confectionery plant |
| Mexico | 1 | 34.5 kV | Substation, Mexico City |
East Asia: 6 projects in 2 countries
| Country | Projects | Voltage | Representative application |
|---|---|---|---|
| Mongolia | 4 | 35 kV | Oyu Tolgoi copper mine phases 1 and 2; Khovd city substation |
| South Korea | 2 | 22-154 kV | Songdo business district; tidal power station |
Three countries account for the largest share: Myanmar (10 projects, mostly 35 kV mine and industrial substations), Vietnam (8, steel plants and hydro stations) and DR Congo (6, mining and chemical plants). That concentration is typical of export work – a first project in a country is usually followed by others once the panel builder or EPC contractor has used the equipment once.
What the Track Record Shows
Mining is the largest single sector. Copper, gold, coal and polymetallic mines in Mongolia, Myanmar, Kyrgyzstan, Laos, DR Congo and Tajikistan. Mine power systems are hard on protection: long feeders, frequent starts, poor power quality and a maintenance team that needs the relay to tell them what happened. Most of these orders were 35 kV substations feeding a processing plant.
Industrial plants of every kind. Steel mills in Vietnam and Tanzania, cement plants in DR Congo and Cambodia, a confectionery factory for a global food group in Brazil, a paper mill in Nigeria, a waste-heat generator at a copper-cobalt mine. In each case the relay panel had to fit an existing switchboard and an existing SCADA.
Utilities and transmission. 66 kV, 110 kV and 220 kV substations for state utilities, including protection and control panels rather than relays alone. These are the projects where the documentation matters as much as the hardware: type test reports, IEC 61850 models, FAT and SAT records.
Renewables and distributed generation. Hydro stations from 4 x 7500 kW to grid-scale, a 2 x 600 MW thermal plant, tidal generation in Korea, waste-to-energy in Turkey. The anti-islanding and reverse power functions in our range come from this work, and from the standard we helped to write.
Commercial and public buildings. Stadiums in South Africa, ports in Lebanon and Oman, airports and hotels in Pakistan, universities in Azerbaijan and the UAE. Smaller projects, but they are where the LV product range gets its field record.
How to Check Any Claim on This Page
Certificates can be verified independently, and we prefer buyers to do it:
- ISO 9001:2015 – certificate 41925Q10467-06R0S. ISO 14001 and ISO 45001 certificates are issued by the same body and scanned on our quality and certifications page.
- Standards – seven Chinese national and energy industry standards we contributed to, listed with their numbers on the same page. They can be looked up in the national standards database.
- Project references – for a tender, we will provide two or three references in the same sector and voltage level, with a contact who has agreed to be called.
- Type test reports – issued by third-party laboratories, available as PDF under NDA or on request.
Reviewed by the relayprotect.com engineering team. Country, voltage level and project type for each entry come from the delivery record; the certificates behind these projects are listed on the quality certifications page.
Related Pages
- Protection relays for power transmission and distribution
- Quality system and certificates
- How to obtain datasheets and manuals
The relay families behind these projects
- Generator protection relays – 87G, 87GT, 64R, 32, 40
- Transformer differential protection – 87T, 87B, 87R, 87V
- Motor protection relays – 87M, 49, 50/51, 46
- Line and feeder protection – 21, 67, 67N, 87L
- Distribution automation terminals – DTU, RTU, IEC 61850
- Protection and control panels – generator, transformer, line
Setting and wiring errors we have caught on live projects, and how each was found before anything was damaged: field notes.
